CS486 - Senior Capstone Design
Guidelines for Status Reporting


Description
One of the most common problems encountered in a project occurs when the customer is not kept informed about the project's status. The customer may assume that everything is moving along smoothly only to be surprised to find out that problems were encountered. Alternatively, the customer may have the sense that nothing is getting done even when things are moving along smoothly. A weekly report on the project status will go a long way toward eliminating misunderstandings between the design team and the client and help to avoid any unwanted surprises for the customer. Status reports also provide the customer with a chance to give input into decisions before it is too late.

It is important that a status report be honest and should not be apologetic. If the project is behind schedule, it is better to inform the customer rather than give the impression that all is well. Do not sugar coat your status reports. Let them be an accurate record of the process.

Specifications
A weekly team status report must be emailed to the client, the project manager, and all team members. Set a standard day for this, i.e. 5:00 pm Friday. The status report should contain the following information:

  1. Meeting Summary: Summarize any team meetings that took place during the week. Communicate when, how long and what was accomplished. Also communicate any key action items that were generated.
  2. Progress Report: Brief description of progress made to date, identifying those specific tasks previously scheduled that have been accomplished.
  3. Problem Report: Identify those previously scheduled tasks that are behind schedule or appear to be in technical trouble. Specify the exact action items that will be employed to accommodate each problem.
  4. New Tasks: Identify any new tasks that must be added to the original schedule. Specify the exact action items that will be employed to accommodate each new task.
  5. Individual Status Reports: For each team member a short paragraph detail tasks completed, tasks started, new tasks assigned and any key information that relates problems encountered or progress achieved. Also include how much time was spent on the project.

REMEMBER: Keep your team status report brief and to the point. Summarize key achievements and tasks. Leave the details for verbal discussion.

Implementation Details
I recommend that you come up with a standardized template for your reports to ensure that they are uniform and complete.

You should post your status reports on your team website, as well as printing out a copy for the project notebook. It is acceptable to email the client a hotlink to the status report on your website rather than the document itself. In this case, you would write an email saying hello, briefly overviewing (2-3 sentences) project progress, then inviting the client to peruse a hotlink to the status report for details.